22 January 2019
Network Rail are carrying out a project to renew the signalling along the railway line between Norwich and Lowestoft and will be undertaking signalling commissioning activities over 9 days between Saturday 23 March and Monday 1 April 2019.
During the first weekend (Saturday 23 – Sunday 24 March), Reedham swing bridge will be under the control of the signalling tester in charge and will be locked down in either the open or closed position – depending on the testing activities being carried out. During this time the bridge will be out of use to river traffic for a period of 12-18 hours, mostly over the night time period.
More detailed information will be posted as and when it becomes available, but vessels wishing to access under this bridge need to make advanced plans during the above project.